3-4 Deposits And Escrows

3-4 Deposits and Escrows.

In every case, we attempt to complete compliance actions and resolve any disputes before the project is completed and final payments are made. Sometimes, corrective actions or disputes continue after completion and provisions must be made to ensure that funds are available to pay any wage restitution that is ultimately found due. In these cases, we allow projects to proceed to final closing and final payments provided the prime contractor deposits an amount equal to the potential liability for wage restitution and liquidated damages, if necessary, in a special account. The deposit or escrow account is controlled by the contract administrator. When a final decision is rendered, the contract administrator makes disbursements from the account in accordance with the decision. Deposit/escrow accounts are established for one or more of the following reasons:

Remember, the prime contractor is responsible and will be held liable for any wage restitution that is due to any worker employed in the construction of the project, including workers employed by subcontractors and any lower-tier subcontractors. See 1-4, Responsibility of the Principal Contractor, and 2-8, Restitution for Underpayment of Wages.

  1. Where the partieshave agreed toamounts of wagerestitution that are due but the employer hasn’t furnished evidence yet that all of the underpaid workers have received their back wages, e.g., some of the workers have moved and could not be located. The amount of the deposit is equal to the total gross amount of restitution due to workers lacking payment evidence. As these workers are paid and proper documentation is provided to the contract administrator, amounts corresponding to the documented payments are returned to the depositor. Amounts for any workers who cannot be located are held in the deposit/escrow account for three years and disposed as described in 2-8(f) of this Guide.
  2. Where underpaymentsare suspected oralleged and aninvestigation hasnot yet been completed. The deposit is equal to the amount of wage restitution and any liquidated damages, if applicable, that are estimated to be due. If the final determination of wages due is less than the amount estimated and placed in the escrow account, the escrow will be reduced to the final amount and the difference will be returned to the depositor.

    If the parties agree to the investigative findings, the amounts due to the workers will be paid by the employer. As these workers are paid and proper documentation is provided to the contract administrator, the gross amounts corresponding to the documented payments are returned to the depositor.
    1. If the employer is unable to make the payments to the workers, e.g., lacks the funds necessary, the contract administrator may make disbursements directly to the workers in the net amounts calculated by the employer. The amounts withheld from the workers for tax deduction will be returned to the employer as payments to workers are made. The employer shall be responsible for reporting and transmitting withholdings to the appropriate agencies.
    2. If the employer is not cooperating in the resolution, the contract administrator shall make disbursements to the workers in accordance with the schedule of wages due. Amounts for unfound workers will be retained as described above (See 2-8(f) and 3-4(a)).

      If the parties do not agree and an administrative hearing is requested, the escrow will be maintained as explained in 3-4(c), below.

      Remember, if you have any questions or need assistance concerning labor standards requirements help is always available. Contact the contract administrator for the project you’re working on or the HUD Field Labor Relations staff in your area.
  3. Where the partiesare waiting forthe outcome ofan administrative hearing that has been or will be requested contesting a final determination of wages due. The deposit shall be equal to the amount of wage restitution and liquidated damages, if applicable, that have been determined due. Once a final decision is rendered, disbursements from the escrow account are made in accordance with the decision.


Consulting Services We Provide

  • Review public works preconstruction contracts
  • Monitor DIR contractor/subcontractor certified payrolls
  • Audit labor classification for each worker employed
  • Review DIR pre-DAS 140/142 submissions
  • Review CAC training fund contributions form CAC-2
  • Review DIR Fringe Benefits Statement PW-26
  • Monitor DIR wage determinations
  • Audit fringe benefits allowances
  • Review DIR holiday payment requirements
  • Audit DIR travel & subsistence requirements
  • Caltrans Labor Compliance
  • County of Sacramento Labor Compliance
  • City of Los Angeles Labor Compliance
  • Los Angeles Unified School District Labor Compliance
  • Federal Davis-Bacon Project Monitoring
  • Federal DBE Implementation & Review
  • Federal FAA AIP Goal Setting
  • DIR & Davis-Bacon Training
  • DIR Civil Wage Penalty Review
  • Local-Hire Review (e.g., San Francisco)
  • Skilled and Trained Workforce

Give us a call to discuss your labor compliance requirements.

This email is intended for general information purposes only and should not be construed as legal advice
or legal opinions on any specific facts or circumstances.

 